How the days are counted
The calculator counts calendar days from the first date to the second. It works on dates rather than times, so clock changes in spring and autumn can’t make the answer an hour short. Leap days are counted when they fall in between.
- Days: the number of days you’d have to wait from the start date to reach the end date.
- Weeks and days: the same, in whole weeks and the days left over.
- Months and days: whole calendar months counted on from the start date, then the days left.
- Working days: Monday to Friday, skipping bank holidays for the part of the UK you pick.
Worked example
From Saturday 14 March 2026 to Sunday 15 November 2026 is 246 days. That’s 35 weeks and 1 day, or 8 months and 1 day. Counting both dates, it’s 247 days.
Over Christmas, from Monday 21 December 2026 to Friday 8 January 2027 there are 19 calendar days but only 12 working days in England and Wales, as 3 bank holidays and 4 weekend days are skipped. Here both dates are counted.
Quick reference
| Span | Days | Counting both dates |
|---|---|---|
| A week | 7 | 8 |
| 30 days from 1 January | 30 | 31 |
| 1 January to 31 December | 364 | 365 |
| A whole year (2026) | 365 | 366 |
| A leap year (2028) | 366 | 367 |
Common mistakes
- Counting the end date twice, or not at all. “From 1 to 2 January” is 1 day apart, but covers 2 days. Decide which you need and use the tick box.
- Assuming every month is 30 days. 31 January to 1 March is 29 days, not 30. In a leap year, February has 29 days: 1 February to 1 March 2028 is 29 days.
- Treating “a month” as 4 weeks. A month is 28 to 31 days. Four weeks is always 28.
- Forgetting bank holidays in a deadline. If something is due in “10 working days”, use the working days calculator, which skips them.
Related tools
- Date calculator: add or take away days, weeks or months.
- Age calculator: your exact age in years, months and days.
- Countdown timer: a live countdown to a date, to share.